Tag Archives: Restoration Strategies

Aerials of EAA’s A-1 & A-2, SLR/IRL

jxpf41485179455-2
Map giving an idea of location of A-1 and A-2
img_2790
A-1 with A-2 in distance

EAA=Everglades Agricultural Area

A-1 is a Flow Equalization Basin located above Strom Water Treatment Area 3/4 that today is part of a state program for EAA water quality improvement called “Restoration Strategies.”  The A-1 was once was part of the Comprehensive Everglades Restoration Plan’s EAA Reservoir.

A-2 is to A-1’s  west and is presently in agricultural use but scheduled to become another Flow Equalization Basin as part of the Central Everglades Planning Project coordinated by the South Florida Water Management District and the Army Corp of Engineers.

__________________________

Over the weekend, I asked my husband, Ed, to fly me over the A-1 and A-2. He rolled his eyes as he does when I use “acronyms speak,” saying: “Just tell me where you want to go….and get a map.”

I got my old Florida Atlas & Gazetteer that works just fine…

As Ed drank his coffee, I gave him the plan.

img_9622

“Well we’re going to fly west over the C-44 Canal and then go south around Lake Okeechobee until we get to Belle Glade and there we are going to follow the North New River Canal south adjacent to Highway 27 until the bend, and the A-1 and A-2 should be just past there….”

Ed looked at me like I was crazy, smiling; I remind him that’s why he loves me and we were off!

Today I am sharing our photos of the area of the A-1.

Sit back and enjoy the flight…

Jacqui

img_2819
A-1 with A-2 lands in distance

file-page1

CEPP:http://141.232.10.32/pm/projects/proj_51_cepp.aspx
Restoration Strategies:https://www.sfwmd.gov/our-work/restoration-strategies
EAA Reservoir what was completed before change to FEB:http://www.barnard-inc.com/projects/environmental/eaa-a-1-reservoir-environmental
Senate President Joe Negron’s Reservoir goal:http://www.sun-sentinel.com/local/palm-beach/fl-lake-okeechobee-reservoir-negron-20160809-story.html

Why #SupportJoeNegron ‘s EAA Reservoir? Because it Should Have Already Been Built! SLR/IR

Image 1-8-17 at 3.50 PM.jpg
CEPP, 2000.
img_9231-version-2
“A1” Reservoir was never built but rather the A1 Flow Equalization Basin instead

In my opinion, one should support Senator Negron’s controversial land purchase to build an EAA Reservoir, because the Reservoir should have already been built. It is a project that has been expected for almost two decades.

A summary–

Due to water quality lawsuits against sugarcane growers, during the 1980s and 90s, the State of Florida had to build six Storm Water Treatment Areas to clean runoff water using Everglades Agricultural Area land, taking valuable sugarcane out of production. (Orange shows STAs) Unfortunately, the industry brought this upon itself as for many years its water runoff had been polluting Everglades National Park and Tribal Lands.

.STA

The problem was so bad, that on top of the Stormwater Treatments Areas, Congress appropriated the beginnings of the Comprehensive Everglades Restoration Plan. Yes, “CERP” has a plan for  “EAA Storage.” A Reservoir, to be the heart of clean water flowing south. (See 4 down left of image below)  CERP (https://www.nps.gov/ever/learn/nature/cerp.htm)
image-1-8-17-at-3-50-pm

Ev. Restoration.gov:http://141.232.10.32/pm/projects/proj_08_eaa_phase_1.aspx

At the beginning of CERP it was determined that the Reservoir/s were to be built near Stormwater Treatment Areas between the Miami and New River Canals. Although they tried, the SFWMD and ACOE never got very far building the Reservoir/s and, you’ll notice “EAA Storage” is still listed on the ACOE calendar of projects, scheduled to begin in 2021. (http://evergladesrestoration.gov/content/cepp/meetings/012512/Recap_EAA_Reservoirs.pdf)

fullsizerender-2
This shows an area of the EAA Reservoir/s proposed between the Miami and New River Canals.

“Why?” You might ask, “didn’t the EAA Reservoir/s get built ?”

ACOE’s IDS or Schedule of Projects: http://www.saj.usace.army.mil/Missions/Environmental/Ecosystem-Restoration/Integrated-Delivery-Schedule/

IMG_3459
Close up of latest ACOE IDS schedule. EAA Storage in white.

The Reservoir/s did not get built because Gov. Charlie Crist’s proposed an idea of US Sugar’s to purchase all of United States Sugar Corporation’s land. This did not work out, induced a halt to the building of the Reservoir, and caused great discord with the Water Management Districts and the state Legislature.  The Great Recession also made the full purchase very difficult.(http://www.nytimes.com/2010/03/08/us/08everglades.html)(http://articles.sun-sentinel.com/2009-09-11/news/0909100559_1_everglades-restoration-reservoir-construction-reservoir-project)

Then on top of the US Sugar and the Recession situation, a Federal law suit that had been dragging on for years was settled and really changed things for the Reservoir/s. In 2010, Governor Rick Scott, “negotiated” a long-standing EPA law suit agreeing that the state of Florida would build more water quality projects to clean sugarcane runoff in the EAA that continued to destroy fauna and pollute Everglades National Park. This “fix” became known as “Restoration Strategies.”(https://www.sfwmd.gov/our-work/restoration-strategies)

Restoration Strategies supplanted CERP’s unfinished EAA Reservoir, building a Flow Equalization Basin instead. Mind you, a shallow treatment area is not a true Reservoir.(https://www.northstar.com/wp-content/uploads/2016/11/SFWMD-EAA-A-1-Flow-Equalization-Basin.pdf)

Now for one last thing…

Just recently, in December of 2016, Congress authorized CEPP. CEPP consist of  six components of CERP mentioned earlier. One of CEPP’s components is the “EAA Reservoir.” This sounds great, but….

CEPP, if appropriated, will not build a Reservoir but yet another Flow Equalization Basin to be located right next to Restoration Strategy’s “A1 Flow Equalization Basin.” This new Flow Equalization Basin will be called the “The A2.” (http://www.saj.usace.army.mil/Missions/Environmental/Ecosystem-Restoration/Central-Everglades-Planning-Project/)

So in conclusion, neither Restoration Strategies nor CEPP will provide the Reservoir that was underway before everything changed in 2008, nor will their water come close to adding up to “a Reservoir.”

Supporting Joe Negron’s land purchase of 60,000 acres is the ground work for building a Reservoir that should have already been built!

#SupportJoeNegron

Support the completion of the EAA Reservoir!

(http://www.miamiherald.com/news/local/environment/article94667592.html)

  • file-page1.jpgThe ACOE has EAA Storage on their construction schedule for 2021. By 2021 the estuaries will surly be dead.file-page1-2